Budget Control ensures that expenditure commitments remain within the budget approved for the Organization. It provides an additional financial control by preventing commitments from being processed when the authorised budget has been exceeded.

Principles

Budget Control is performed at the level of a Budget Control Unit (BCU), which groups one or more budget codes. By default, BCUs for operational expenditure are defined at Department and Programme level. For projects, the standard structure depends on the project type. It is the responsibility of the Processes and Finance Support Service (FAP-PFS) to build and maintain the Budget Control structure. At the request of the DPO and with the approval of the FAP-FPC financial analyst, BCUs may be customized for specific activities.

For each BCU, the system compares for the current year:

  • The Available Budget allocated to the BCU;
  • The Existing Commitments recorded against the BCU.

A BCU becomes overcommitted when commitments exceed the Available Budget.

Budget Control may include an authorised tolerance, expressed as a percentage of the Available Budget. This defines the Authorised Budget, allowing a limited level of overcommitment before budget control starts blocking.

Two outcomes are possible:

  • Warning: commitments exceed the Available Budget but remain within the Authorised Budget. The transaction can continue through the approval workflow.
  • Blocking control: commitments exceed the Authorised Budget. The commitment is placed on hold and must be reviewed by the responsible Financial Analyst from FAP-FPC before it can proceed.

1. How is the Available Budget and Authorised Budget calculated?

The Available Budget of a BCU is the sum of the budgets available on all budget codes belonging to the BCU. These amounts are recorded in the Payment Budget field in CET.

The Authorised Budget of a BCU is the sum of the budgets authorised for commitments on all budget codes belonging to the BCU. These amounts are recorded in the Commitment Budget field in CET. At the request of the DPO and with the approval of the FAP-FPC financial analyst, the tolerance level may be customized by FAP-PFS.

2. When is Budget Control triggered?

Budget control operates at two levels:

  • EDH:
    During the creation and approval of financial requests (DAI, OSVC, etc.), a budget availability check is performed. This early validation informs users when the planned expenditure may exceed the available budget and avoids unnecessary processing of requests that cannot be funded.
  • CEGID XRP (Qualiac):
    A second budget control is performed when the commitment is created in the Enterprise Resource Planning (ERP). If the Authorised Budget has been exceeded, the commitment is placed on hold until the situation has been reviewed and appropriate action has been taken by the responsible Financial Analyst.

3. Annual calendar

FAP-PFS activates the budget control normally at the end of May, once internal budget allocations have been completed and budget data has been loaded into CEGID XRP (Qualiac) by FAP. Budget control is deactivated at year-end to facilitate the financial closing activities and the transition to the new budget year.